STEP-1
Setting out and demarcation of security pass office
and customs building Project area in detail.
STEP-2
Determination of soil bearing capacity at O.G.L for
foundations design.
STEP-3
Filling and compaction to foundation formation level
in layers of 150mm compacted thickness, carrying out compaction test for each
layer.
STEP-4
Excavation for underslab drainage, etisalat,
electrical, water supply services and necessary accessories. Backfill in layers
to floor slab and footing formation level.
STEP-5
Cutting and Compaction for foundation thickenings of
load bearing and non-load bearing foundations forming side slopes in
excavation.
STEP-6
Fix side shuttering for all external load bearing
foundations, 1000 gauge polythene sheets
over floor slab and footing area.
STEP-7
Fix steel reinforcement to footings and floor slab
area in accordance with structural design details and approved bar bending
schedules.
STEP-8
Lay uPVC electrical conduits through floor slab as
indicated in proposed electrical layout.
STEP-9
Cast footings and floor slab using MSRC 40/20
concrete poured by pump or direct discharge from truck mixer, following casting
cure slab by covering with Hessian and watering.
STEP-10
Block work- bridge openings for doors and windows
with pre-cast lintels.
STEP-11
Continue blockwork over lintels to U/S of framing
beams.
STEP-12
Shuttering for 250mm high drop beams and roof slab
soffit.
STEP-13
Fix reinforcement for drop beams and roof slab
according to structural design.
STEP-14
Lay uPVC
electrical conduits and other services (eg. rain water outlet for down
pipes).
STEP-15
Cast drop beams and roof slab using concrete pump and
cure structural elements by covering with Hessian and watering.
STEP-16
Shuttering for parapet external walls, followed by steel
reinforcement.
STEP-17
Cast parapet walls using concrete pump.
STEP-18
Roofing system lay 50mm light weight concrete screed,
4mm torch applied membrane over primed surface, 50mm extruded polystryene board
and 50mm thick washed rounded wadi gravel.
STEP-19
Chase blockwork for embedded electrical, fire
fighting, water supply and AC power cables.
STEP-20
Internal and External plastering cement/sand mortar.
STEP-21
Install doors, windows, counter and kitchen wall
units etc.
STEP-22
Lay floor screed followed by 8mm floor tiles
(grannitto ceramic). Tiles to be fixed with glue. Wall tiles (6mm thick
ceramic) on walls of toilet and kitchen , skirting tiles matching with floor.
STEP-23
Sanitary fittings (W.C, Wash basins, kitchen sink),
light fittings with accessories, fire fighting and AC works etc.
STEP-24
External walls and parapet "JEOTATEX"
painting system along with 2 coats of Weathertough emulsion.