STEPS INVOLVED TO CONSTRUCT THE BUILDING



STEP-1

Setting out and demarcation of security pass office and customs building Project area in detail.

STEP-2

Determination of soil bearing capacity at O.G.L for foundations design.

STEP-3

Filling and compaction to foundation formation level in layers of 150mm compacted thickness, carrying out compaction test for each layer.

STEP-4

Excavation for underslab drainage, etisalat, electrical, water supply services and necessary accessories. Backfill in layers to floor slab and footing formation level.

STEP-5

Cutting and Compaction for foundation thickenings of load bearing and non-load bearing foundations forming side slopes in excavation.

STEP-6

Fix side shuttering for all external load bearing foundations,  1000 gauge polythene sheets over floor slab and footing area.

STEP-7

Fix steel reinforcement to footings and floor slab area in accordance with structural design details and approved bar bending schedules.

STEP-8

Lay uPVC electrical conduits through floor slab as indicated in proposed electrical layout.
STEP-9

Cast footings and floor slab using MSRC 40/20 concrete poured by pump or direct discharge from truck mixer, following casting cure slab by covering with Hessian and watering.

STEP-10

Block work- bridge openings for doors and windows with pre-cast lintels.

STEP-11

Continue blockwork over lintels to U/S of framing beams.

STEP-12

Shuttering for 250mm high drop beams and roof slab soffit.

STEP-13

Fix reinforcement for drop beams and roof slab according to structural design.

STEP-14

Lay uPVC  electrical conduits and other services (eg. rain water outlet for down pipes).

STEP-15

Cast drop beams and roof slab using concrete pump and cure structural elements by covering with Hessian and watering.

STEP-16

Shuttering for parapet  external walls, followed by steel reinforcement.

STEP-17

Cast parapet walls using concrete pump.

STEP-18

Roofing system lay 50mm light weight concrete screed, 4mm torch applied membrane over primed surface, 50mm extruded polystryene board and 50mm thick washed rounded wadi gravel.
STEP-19

Chase blockwork for embedded electrical, fire fighting, water supply and AC power cables.

STEP-20

Internal and External plastering cement/sand mortar.

STEP-21

Install doors, windows, counter and kitchen wall units etc.

STEP-22

Lay floor screed followed by 8mm floor tiles (grannitto ceramic). Tiles to be fixed with glue. Wall tiles (6mm thick ceramic) on walls of toilet and kitchen , skirting tiles matching with floor.

STEP-23

Sanitary fittings (W.C, Wash basins, kitchen sink), light fittings with accessories, fire fighting and AC works etc.

STEP-24

External walls and parapet "JEOTATEX" painting system along with 2 coats of Weathertough emulsion.





2 comments:

  1. This comment has been removed by the author.

    ReplyDelete
  2. That said, simply because you've got work which happens to be based in the US it doesn't mean that you are learning everything that you can or should be. You can find more details on kamurjshin on the site kamurjshin.am/en/.

    ReplyDelete

INTERVIEW Q&A for Geo-Technical Investigation and Geological Materials and Ground Water

INTERVIEW QUESTIONS & ANSWERES Geo-Technical Investigation and Geological Materials and Ground Water Note: Below information is given as...